Section 179D After the June 30, 2026 Cutoff: What Hot Water and HVAC Projects Can Still Claim

This is the main image for the blog hero section. It shows a current image related to the blog.

Section 179D names hot water systems in its text, and as of this article's date it is closed to new starts. The One Big Beautiful Bill Act, Public Law 119-21 of July 4, 2025, added a termination to the statute: the deduction “shall not apply with respect to property the construction of which begins after June 30, 2026.”

That is a construction-start test, not a placed-in-service test. A heat pump water heating plant that broke ground in spring 2026 and comes online in 2027 is still inside the statute; one bid in September 2026 is not. The deduction will therefore be claimed on 2026, 2027 and 2028 returns for projects already underway. This article is not tax advice; every project needs a tax adviser.

In short, 179D allows a deduction equal to the cost of energy efficient commercial building property, capped at a per-square-foot amount, for property that is part of interior lighting, HVAC and hot water systems, or the building envelope. The property must be certified to reduce total annual energy and power costs for those systems by at least 25 percent against an ASHRAE 90.1 reference building.

The 2025 amounts are $0.58 per square foot at 25 percent savings rising $0.02 per percentage point to $1.16, or $2.90 rising $0.12 per point to $5.81 when prevailing wage and apprenticeship requirements are met. The 2026 maximums are $1.19 and $5.94. An alternative path for buildings at least five years old uses a measured 25 percent reduction in energy use intensity and is claimed in the year of final certification, which comes more than a year after the retrofit is placed in service.

For buildings owned by governments and tax-exempt organizations, the deduction goes to the designer. None of it applies to property whose construction begins after June 30, 2026.

What the statute covers, and where hot water sits

Section 179D(c)(1) defines energy efficient commercial building property as property that is depreciable or amortizable, located in the United States, within the scope of ASHRAE/IES Standard 90.1, and installed as part of one of three systems: the interior lighting systems; the heating, cooling, ventilation and hot water systems; or the building envelope. A central heat pump water heating plant, its storage tanks, pumps, mixing valves and controls are hot water system property under that definition. The questions are whether the certified plan clears the 25 percent test and whether construction began in time.

The test is cost-based. The plan must reduce the total annual energy and power costs of the three systems combined by at least 25 percent compared with a reference building that meets Standard 90.1. The reference edition is the more recent of 90.1-2007 or the most recent edition DOE has finalized and the Secretary has affirmed no later than four years before the property is placed in service. Calculations follow regulations based on the California Nonresidential Alternative Calculation Method and must use qualified software from DOE's list. DOE's 179D Portal gives estimates only and cannot be used to claim the deduction. Certification includes an owner notice of the energy features and projected annual energy costs, with inspections by individuals recognized by a Secretary-certified organization.

Two features of the test matter for a hot water plant. First, it is a whole-systems test: the hot water plant's savings are counted together with lighting, HVAC and envelope. Second, it is measured in cost, not energy. Whether the qualified software credits a lower-cost tariff period for a plant that charges storage overnight depends on the rate inputs the software accepts; the project's modeler should confirm that before the storage is counted on anything other than its efficiency.

The amounts, by year

Section 179D(b) sets the statutory rates and 179D(g) indexes them for inflation for tax years beginning after 2022. The amounts are per square foot of the building:

  • 2023: $0.50 at 25 percent savings, plus $0.02 per percentage point above 25, to a maximum of $1.00; with prevailing wage and apprenticeship, $2.50 plus $0.10 per point to $5.00.
  • 2024: $0.57 plus $0.02 per point to $1.13; with prevailing wage and apprenticeship, $2.83 plus $0.11 per point to $5.65.
  • 2025: $0.58 plus $0.02 per point to $1.16; with prevailing wage and apprenticeship, $2.90 plus $0.12 per point to $5.81.
  • 2026: Maximums of $1.19 and $5.94 per the draft Instructions for Form 7205 (Rev. December 2025). The base and per-point figures for 2026 are in the final instructions and must be confirmed.

Caps, basis and prevailing wage

The maximum is reached at 50 percent savings. The deduction is the cost of the qualifying property, limited to the per-square-foot amount times the building's square footage, less any 179D deductions claimed for the same building in the three preceding tax years. The basis of the property is reduced by the deduction taken, which matters for depreciation and for any other incentive computed on basis.

Prevailing wage and apprenticeship multiply the deduction by five. The statute requires laborers and mechanics to be paid at least the locally prevailing rates set by the Secretary of Labor and applies the apprenticeship rules of section 45(b)(8), with the correction and penalty rules of section 45(b)(7)(B). For a project that already met those requirements for a 48E credit on the storage, the documentation serves both.

The alternative retrofit path

Section 179D(f) is written for existing buildings and fits a hot water retrofit better than the modeling path. The building must have been placed in service at least five years before the qualified retrofit plan is established; the plan must be prepared by a licensed architect or engineer and target a 25 percent or greater reduction in the building's energy use intensity against its baseline; and the deduction is claimed in the year of the qualifying final certification, which certifies that the measured, weather-adjusted EUI is not more than 75 percent of baseline.

DOE's page gives the measurement windows: the pre-upgrade EUI is certified for a date within the one-year period ending on the placed-in-service date, and the post-upgrade EUI for a date more than one year after it. The amount is the lesser of the per-square-foot figure computed from the certified reduction and the adjusted basis of the retrofit property.

The retrofit path has three consequences under the cutoff. The EUI test is site energy, not cost, so the site EUI metrics article applies: a heat pump replacing an 80 percent boiler cuts the hot water share of site EUI by 1 − 0.80 / COP, 68 percent at a COP of 2.5. The measurement wait means a plant placed in service in late 2026 is certified no earlier than late 2027 and claimed on the 2027 or 2028 return. The construction-start date must be documented now because the claim will be examined years after the cutoff.

Beginning of construction: what is and is not settled

The statute and the IRS FAQ both use the phrase “the construction of which begins after June 30, 2026” and neither defines it. The FAQ, which also covers 25C, 25D, 45L and other sections modified by the same law, defines when a 25D expenditure is made, when installation is completed, but says nothing further about 179D.

An owner or designer should assemble the record for a construction start before July 1, 2026: executed contracts, permits, mobilization dates, invoices for physical work and equipment, and the dated qualified retrofit plan where the (f) path is used. The standard the IRS will apply is not stated in the sources used here; the project's tax adviser should confirm what guidance exists. The article does not assert a physical-work test or a five percent safe harbor for 179D.

Worked example 1: new plant, modeling path

Labeled assumptions: A 100,000 square foot office placed in service in 2025; a new HVAC system, a heat pump water heating plant with thermal storage and an LED lighting retrofit; qualified software models a 40 percent reduction in annual energy and power costs for lighting, HVAC and hot water combined against the 90.1 reference; qualifying property cost $900,000; prevailing wage and apprenticeship requirements met.

  • Savings above 25 percent: 15 percentage points.
  • Rate with prevailing wage and apprenticeship, 2025: $2.90 + 15 × $0.12 = $4.70 per square foot, below the $5.81 cap.
  • Cap: $4.70 × 100,000 = $470,000.
  • Deduction: the lesser of $900,000 of qualifying cost and $470,000, so $470,000, less any 179D deductions for the building in the prior three years.
  • Without prevailing wage and apprenticeship: $0.58 + 15 × $0.02 = $0.88 per square foot, or $88,000.
  • Basis of the property is reduced by the deduction claimed.
  • The same building placed in service in 2026, with construction begun before July 1, 2026, uses the 2026 rates, whose maximums are $1.19 and $5.94; the per-point figures come from the final Form 7205 instructions.

Worked example 2: existing multifamily building, retrofit path

Labeled assumptions: A 150,000 square foot multifamily building placed in service in 2008; a qualified retrofit plan by a licensed engineer established in March 2026; a central heat pump water heating plant with storage replacing gas water heaters, plus envelope air sealing, with construction begun in May 2026 and the plant placed in service in October 2026; retrofit property adjusted basis $650,000; prevailing wage and apprenticeship met; baseline weather-adjusted site EUI 95 kBtu per square foot; hot water at 20 percent of site energy, assumed, from an 80 percent boiler, replaced by a plant at a COP of 2.5.

  • Hot water site energy before: 95 × 0.20 = 19.0 kBtu per square foot of gas.
  • Heat delivered: 19.0 × 0.80 = 15.2 kBtu per square foot thermal.
  • Electricity after, at COP 2.5: 15.2 / 2.5 = 6.1 kBtu per square foot electrical.
  • Hot water reduction: 19.0 − 6.1 = 12.9 kBtu per square foot, or 13.6 percent of the building's EUI.
  • Envelope and other measures, assumed: 12.0 kBtu per square foot, or 12.6 percent.
  • Projected EUI: 95 − 12.9 − 12.0 = 70.1 kBtu per square foot, or 73.8 percent of baseline, inside the 75 percent requirement with little margin.
  • Measurement: post-upgrade EUI certified for a date more than one year after October 2026, so no earlier than late 2027; deduction claimed in the year of final certification.
  • Rate at a 26.2 percent certified reduction, if measured: $2.90 + 1.2 × $0.12 ≈ $3.04 per square foot at 2025 rates, or the applicable year's rate; cap $3.04 × 150,000 = $456,000.
  • Deduction: the lesser of $456,000 and the $650,000 adjusted basis, so about $456,000, subject to the applicable year's inflation adjustment.
  • The margin is the lesson. A 73.8 percent projection against a 75 percent threshold leaves 1.2 kBtu per square foot of room for a mild winter, a COP that lands at 2.2 instead of 2.5, or a standby loss that was not modeled. The heat loss article and the stratification article cover the storage-side margin; the cold-climate article covers the COP margin. A plan that targets 30 percent rather than 25 is the normal engineering response.

How 179D sits next to 48E, elective pay and C-PACE

Section 48E is a credit on the basis of thermal energy storage property and other qualifying energy property; 179D is a deduction against the cost of building systems. The 48E article covers what qualifies and the elective pay article covers how tax-exempt owners take the credit as a payment.

Whether the same dollar of cost can support both a 48E credit and a 179D deduction, and how the 179D basis reduction interacts with the credit's own basis rules, is a tax-adviser question that the sources used here do not answer. The article makes no claim either way.

For a school, hospital district, city or nonprofit owner, 179D's designer allocation sends the deduction to the architect or engineer of record, which is why a design firm may ask for the allocation letter at contract signing. C-PACE financing is indifferent to 179D except that the lender will want to know the net cost, and utility incentives are usually settled before the tax basis is.

Frequently Asked Questions

Is the 179D deduction still available?

For property whose construction began on or before June 30, 2026, yes; the statute does not apply to property the construction of which begins after that date. Claims for earlier starts are made on the return for the placed-in-service year, or for the retrofit path the year of final certification.

What does beginning of construction mean for 179D?

Neither the statute text nor the IRS FAQ used for this article defines it. Document the construction start with contracts, permits and dated physical work, and confirm with a tax adviser whether the IRS has issued guidance.

Do hot water systems qualify for 179D?

Hot water systems are named in 179D(c)(1) alongside heating, cooling, ventilation, interior lighting and the envelope. The property must be within the scope of ASHRAE 90.1 and part of a certified plan that reduces the combined annual energy and power costs of those systems by at least 25 percent.

How much is the deduction per square foot?

For 2025, $0.58 at 25 percent savings rising $0.02 per point to $1.16, or $2.90 rising $0.12 per point to $5.81 with prevailing wage and apprenticeship. The 2026 maximums are $1.19 and $5.94 per the draft Form 7205 instructions.

What is the alternative retrofit deduction?

A path for buildings placed in service at least five years before a qualified retrofit plan by a licensed architect or engineer, based on a measured 25 percent reduction in weather-adjusted EUI, claimed in the year of final certification, which comes more than one year after the retrofit is placed in service. The amount is the lesser of the per-square-foot figure and the adjusted basis of the retrofit property.

Can a nonprofit or school use 179D?

Not directly; for buildings owned by government bodies, tribal governments, Alaska Native Corporations and tax-exempt organizations, the deduction is allocated to the designer.

Does thermal energy storage count toward 179D?

Storage installed as part of the hot water or HVAC system is within the named systems. It counts toward the 25 percent test through the savings the certified plan attributes to it; whether a lower-cost charging period is credited depends on the qualified software's rate inputs.

What other credits ended with the same law?

45L ends for homes acquired after June 30, 2026; 25C ends for property placed in service after December 31, 2025; and 25D ends for expenditures made after December 31, 2025, with an expenditure made when installation is complete.

The bottom line

179D is closed to projects that start construction after June 30, 2026 and open to those that started before, which means the deduction will be claimed for the next two to three years on plants now being built. Hot water systems are named in the statute; the test is 25 percent of combined system energy cost against ASHRAE 90.1, or 25 percent of measured EUI for an older building; and the amounts run to $5.81 per square foot for 2025 and $5.94 for 2026 with prevailing wage and apprenticeship.

Document the construction start now, model the plant with margin above 25 percent, check the incentive finder for the state programs that stack with it, and take the whole package to a tax adviser before any figure goes into a pro forma. This article is not tax advice.

Explore the right thermal

energy solution for your project.

Tell our team about your building, operating goals, and energy needs.

Get in touch

Let's review your project

Send us a message and our team of experts will get right back to you — or grab a time on our calendar below.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
Address
900 South Glaspie Street, Oxford, MI 48371 USA

Prefer to book a time? Grab a slot below