Boston's standard is an emissions limit, not an energy target. The Building Emissions Reduction and Disclosure Ordinance, amended in 2021 and known as BERDO 2.0, has applied to large buildings since 2025 and reaches zero in 2050.
A multifamily building of 35 units or more is allowed 4.1 kgCO2e per square foot through 2029 and 2.4 kgCO2e per square foot from 2030. A building above its limit may pay $234 for every metric ton above it, while emissions-standard violations can carry fines of up to $1,000 per day.
The City's projected electricity factor falls from 249 kgCO2e per MWh in 2025 to 150 kgCO2e per MWh in 2050. Electrification therefore produces a larger emissions reduction in later compliance periods. For a gas-heated building, domestic hot water is usually the first load to electrify because it operates year-round.
In short, BERDO covers non-residential buildings of 20,000 square feet or more and residential buildings of 15 units or more, with parcels that combine to those sizes counted together. Buildings of 35,000 square feet or 35 units and larger have been subject to the emissions standards since the 2025 reporting year. Smaller covered buildings report now and come under the standards in 2031 for their 2030 emissions.
Reporting is due May 15 each year through ENERGY STAR Portfolio Manager, with third-party verification in 2026 and every five years. The multifamily limits are 4.1, 2.4, 1.8, 1.1, 0.6 and 0 kgCO2e per square foot across the six periods to 2050. Emissions are calculated at 53.11 kgCO2e per MMBtu for gas and the City's annual grid factor.
On labeled assumptions, a 200-unit building at 3.37 kgCO2e per square foot is under the 2025 limit, 204 metric tons over the 2030 limit, and reduces emissions by 81 metric tons when domestic hot water is electrified with a heat pump plant.
In this article
- Who is covered and when the standards bite
- The limits, by use, to 2050
- How emissions are counted
- Alternative compliance payments, fines and flexibility
- Worked example: a 200-unit multifamily building
- Why storage decides the plant that fits
- A BERDO sequence for a gas-heated building
- Frequently Asked Questions
- The bottom line
Who is covered and when the standards bite
The ordinance covers a non-residential building of 20,000 or more square feet of gross building area where at least 50 percent is non-residential use, and a residential building of 15 or more dwelling units where units and common space exceed 50 percent of gross area. Parking is excluded in both cases. A parcel under one owner with several buildings that together reach 15 units or 20,000 square feet is covered as a group.
Per BERDO Basics, a building is residential if 50 percent or more of gross floor area, excluding parking, is residential.
Buildings of at least 35,000 square feet or 35 units have been under the standards from the first period, 2025-2029. Buildings from 20,000 to under 35,000 square feet, or 15 to under 35 units, report energy and water use now but are not subject to the standards until 2031, when they report 2030 emissions. They start at the 2030-2034 limit rather than the 2025-2029 limit. For a 25-unit building, that is the difference between 4.1 and 2.4 kgCO2e per square foot on day one.
Every covered building reports through ENERGY STAR Portfolio Manager by May 15 for the prior calendar year. Third-party verification is required in the first reporting year, the first emissions compliance year, and in verification years set as 2022, 2026 and every five years after.
Owners with New York City buildings will recognize a similar structure from Local Law 97, which also caps emissions per square foot with its own coefficients.
The limits, by use, to 2050
The ordinance's Table 1 sets the standard in kgCO2e per square foot per year for thirteen building uses. A building defaults to the standard of its largest primary use. Mixed-use buildings may use a blended standard weighted by area.
- Assembly: 2025-2029 7.8; 2030-2034 4.6; 2035-2039 3.3; 2040-2044 2.1; 2045-2049 1.1; 2050 onward 0.
- College/University: 10.2; 5.3; 3.8; 2.5; 1.2; 0.
- Education: 3.9; 2.4; 1.8; 1.2; 0.6; 0.
- Food Sales and Service: 17.4; 10.9; 8.0; 5.4; 2.7; 0.
- Healthcare: 15.4; 10.0; 7.4; 4.9; 2.4; 0.
- Lodging: 5.8; 3.7; 2.7; 1.8; 0.9; 0.
- Manufacturing/Industrial: 23.9; 15.3; 10.9; 6.7; 3.2; 0.
- Multifamily Housing: 4.1; 2.4; 1.8; 1.1; 0.6; 0.
- Office: 5.3; 3.2; 2.4; 1.6; 0.8; 0.
- Retail: 7.1; 3.4; 2.4; 1.5; 0.7; 0.
- Services: 7.5; 4.5; 3.3; 2.2; 1.1; 0.
- Storage: 5.4; 2.8; 1.8; 1.0; 0.4; 0.
- Technology/Science: 19.2; 11.1; 7.8; 5.1; 2.5; 0.
What the step-down means for hot water planning
The 2030 step is the steep one: multifamily drops 41 percent, office drops 40 percent and retail drops 52 percent. The floor is zero in 2050, which no fuel-burning plant can meet.
How emissions are counted
The BERDO Regulations fix the method. Natural gas, propane, fuel oil, diesel and kerosene use the most recent ENERGY STAR Portfolio Manager factors unless the Review Board approves another source.
The June 2024 Emissions Factors List gives natural gas at 53.11 kgCO2e per MMBtu, No. 2 fuel oil at 74.21 and propane at 64.25.
Electricity uses a grid factor that the Environment Department sets by April 15 each year from ISO New England and NEPOOL data. If the date is missed, the lower of the previous year's factor or the projected factor applies. The 2023 measured factor was 270 kgCO2e per MWh.
District energy factors are allocated by output stream in proportion to each stream's energy content divided by its production efficiency, with annual third-party verification. Published 2023 steam factors are 55.2 for Vicinity Boston, 51.6 for the Longfellow Loop and 63.7 for MATEP, against a 66.40 default.
The BERDO Policies and Procedures Version 5, adopted September 14, 2026, publishes the projected grid trajectory used for planning.
- 2025: 249 kgCO2e per MWh.
- 2026: 242 kgCO2e per MWh.
- 2027: 265 kgCO2e per MWh.
- 2028: 265 kgCO2e per MWh.
- 2029: 264 kgCO2e per MWh.
- 2030: 259 kgCO2e per MWh.
- 2035: 231 kgCO2e per MWh.
- 2040: 198 kgCO2e per MWh.
- 2045: 173 kgCO2e per MWh.
- 2050: 150 kgCO2e per MWh.
Alternative compliance payments, fines and flexibility
A building above its limit may make an alternative compliance payment of $234 per metric ton of CO2e over the limit. This is an initial amount that the Review Board reviews every five years and may adjust by regulation. Payments fund projects in environmental justice communities. The payment is a choice; the fine is not.
For buildings over 35,000 square feet or 35 units, fines are $300 per day for failure to meet reporting requirements and $1,000 per day for failure to meet the emissions standard. Inaccurate reporting carries fines of $1,000 to $5,000. The smaller tier faces $150 per day for reporting failures and $300 per day for emissions-standard failures. Fines continue to accrue after an assessment is issued.
The City issues a notice of probable violation at least 60 days before a notice of violation, or 90 days for verification discrepancies. Penalties are assessed within 30 days, and the owner has 21 days to request a reduction.
Four flexibility measures exist: blended emissions standards for mixed-use buildings, which need no Review Board approval; building portfolios, with fines applied per building; individual compliance schedules; and hardship compliance schedules. The last three require Review Board approval.
Portfolio and schedule filings for 2026 emissions are due May 1, 2027. Owners may also buy renewable energy. The City's REC Connector program set October 31, 2026 as the deadline to purchase Massachusetts Class I RECs toward the 2025 standard.
Worked example: a 200-unit multifamily building
The following are labeled assumptions: 200 units; 200,000 square feet of gross building area; coverage under the standards from 2025; gas-fired boilers for space heating and domestic hot water at 40 kBtu per square foot per year, equal to 8,000 MMBtu; electricity at 5 kWh per square foot, equal to 1,000,000 kWh; domestic hot water at 35 percent of gas use; boiler efficiency of 80 percent; and a replacement heat pump water heating plant with an annual COP of 2.5. Thermal and electrical quantities are labeled separately.
The building's limits are 820 metric tons per year for 2025-2029, calculated as 4.1 kgCO2e per square foot × 200,000 square feet; 480 metric tons for 2030-2034; 360 metric tons for 2035-2039; 220 metric tons for 2040-2044; 120 metric tons for 2045-2049; and 0 metric tons from 2050.
- Baseline gas emissions: 8,000 MMBtu × 53.11 kgCO2e per MMBtu = 424,880 kgCO2e, or 424.9 metric tons.
- Baseline electricity emissions at the 2025 projected grid factor: 1,000,000 kWh × 0.249 kgCO2e per kWh = 249,000 kgCO2e, or 249.0 metric tons.
- Baseline total: 673.9 metric tons, equal to 3.37 kgCO2e per square foot, under the 4.1 kgCO2e per square foot 2025-2029 limit.
- 2030 gas emissions: 424.9 metric tons.
- 2030 electricity emissions at the projected 2030 grid factor: 1,000,000 kWh × 0.259 kgCO2e per kWh = 259.0 metric tons.
- 2030 total: 683.9 metric tons, equal to 3.42 kgCO2e per square foot.
- 2030 excess: 683.9 metric tons − 480 metric tons = 203.9 metric tons above the limit.
- 2030 alternative compliance payment before any five-year rate adjustment: 203.9 metric tons × $234 per metric ton = approximately $47,700 per year.
Domestic hot water electrification
The hot water gas share is 8,000 MMBtu × 0.35 = 2,800 MMBtu. At 53.11 kgCO2e per MMBtu, that is 148.7 metric tons.
Useful heat delivered at 80 percent boiler efficiency is 2,800 MMBtu × 0.80 = 2,240 MMBtu thermal. This equals 656,500 kWh thermal per year, or approximately 1,800 kWh thermal per day.
At an annual heat pump COP of 2.5, the plant requires 656,500 kWh thermal ÷ 2.5 = 262,600 kWh electrical per year.
At the projected 2030 electricity factor, heat pump emissions are 262,600 kWh electrical × 0.259 kgCO2e per kWh = 68,000 kgCO2e, or 68.0 metric tons.
The reduction is 148.7 metric tons − 68.0 metric tons = 80.7 metric tons.
The new 2030 total is 683.9 metric tons − 80.7 metric tons = 603.2 metric tons, equal to 3.02 kgCO2e per square foot. The building remains 123.2 metric tons above the 480-metric-ton limit, with an alternative compliance payment of approximately $28,800 per year.
Hot water electrification closes approximately 40 percent of the 2030 gap on these assumptions. The remainder is space-heating gas: 5,200 MMBtu, or 276.2 metric tons.
At the 2035 limit of 360 metric tons and the projected 2035 grid factor of 231 kgCO2e per MWh, hot water conversion alone leaves the building at 567.9 metric tons: 231.0 metric tons from building electricity, 60.7 metric tons from the heat pump plant and 276.2 metric tons from heating gas. Space heating therefore has to follow.
The hot water plant is the first step in this example because it runs year-round and can be built while the boilers stay in service. This is an assumption-based calculation; it does not state that any building complies.
Why storage decides the plant that fits
The assumed daily hot water load is approximately 1,800 kWh thermal. If one-third of the day is treated as the morning peak, the assumed peak is approximately 600 kWh thermal.
The TEHQ 700-gallon module stores 108 kWh thermal at a 35 C, or 63 F, delta. Six modules carry the assumed morning peak at the rated delta before the usable delta is applied.
Each module is 60 inches in diameter and 88.6 inches tall, weighs 6,046 lb filled, imposes 308 lb per square foot, and loses 2.4 F per 24 hours. The modules assemble from panels inside a Boston basement built for a gas plant.
A plant sized to the daily load with that storage draws roughly half the kW of one sized to the morning peak. The NEC 220.87 article covers the measured-demand check, the demand charge article covers tariff arithmetic, and the sizing method article and calculator cover volume.
Storage at 140 F with a master mixing valve is covered in the 140 F article. None of these storage specifications changes the kgCO2e line directly. Storage changes whether the plant fits the electrical service, room and budget.
A BERDO sequence for a gas-heated building
Use the following sequence for an initial BERDO position and hot water electrification plan.
- Confirm the tier from gross building area excluding parking and unit count. Confirm the 2025 or 2031 start.
- Pull the Portfolio Manager record, apply 53.11 kgCO2e per MMBtu for gas and the City's current grid factor, and compute the position against the current period and against 2030 using the projected 259 kgCO2e per MWh factor.
- Separate hot water gas from heating gas with summer bills. Replace the 35 percent placeholder with the building's own share.
- Price a heat pump water heating plant sized to the daily load with storage. Run the electrical check before fixing the design.
- Decide between an individual compliance schedule, a portfolio and alternative compliance payments for the years before the plant is in place. The filing deadline for 2026 emissions is May 1, 2027.
- Coordinate 48E, elective pay for tax-exempt owners and C-PACE through their own articles. Massachusetts utility incentives should be verified with the program administrator.
- Re-verify the ACP rate, the grid factor and any Review Board changes before a figure goes into a capital plan.
Frequently Asked Questions
Which buildings does BERDO cover?
Non-residential buildings of 20,000 square feet or more, residential buildings of 15 or more units, and parcels with multiple buildings that together reach either threshold, excluding parking. A mixed-use building is residential if 50 percent or more of its floor area excluding parking is residential.
When do the emissions standards start?
Buildings of 35,000 square feet or 35 units and larger have been under the standards since the 2025-2029 period. Buildings from 20,000 to under 35,000 square feet or 15 to under 35 units are not subject to the standards until 2031, when 2030 emissions are reported.
What is the BERDO limit for a multifamily building?
The limit is 4.1 kgCO2e per square foot per year for 2025-2029, 2.4 for 2030-2034, 1.8 for 2035-2039, 1.1 for 2040-2044, 0.6 for 2045-2049 and 0 from 2050.
What is the alternative compliance payment?
The initial alternative compliance payment is $234 per metric ton of CO2e above the building's limit. The Review Board reviews the amount every five years.
What are the fines?
For buildings over 35,000 square feet or 35 units, fines are $300 per day for reporting failures and $1,000 per day for emissions-standard failures. The smaller tier faces $150 and $300 per day. Inaccurate reporting carries fines of $1,000 to $5,000. Fines continue to accrue after an assessment.
What emissions factors does Boston use?
Boston uses 53.11 kgCO2e per MMBtu for natural gas from ENERGY STAR Portfolio Manager, a City grid factor set each year by April 15 from ISO New England and NEPOOL data, and district steam factors by provider. The measured 2023 electricity factor was 270 kgCO2e per MWh. The projected factors are 249 kgCO2e per MWh for 2025 and 259 kgCO2e per MWh for 2030.
How much does electrifying hot water reduce emissions under BERDO?
On labeled assumptions, a 200-unit building with hot water at 35 percent of 8,000 MMBtu of gas, an 80 percent boiler and a COP 2.5 heat pump reduces emissions by approximately 81 metric tons per year at the 2030 grid factor. That is approximately 40 percent of its 204-metric-ton gap to the 2030 limit. The building's own data replace every input.
Does thermal storage count toward BERDO compliance?
Not directly. BERDO counts annual kgCO2e. Storage sets the heat pump plant's size, electrical service and demand charges, which determine whether the project can be built and what it costs to run.
The bottom line
BERDO is an emissions cap with a $234 per ton price on excess emissions, a $1,000 per day fine for ignoring the standard, and a 2050 floor of zero.
For a gas-heated multifamily building, the 2030 step from 4.1 to 2.4 kgCO2e per square foot is the period to plan for. On the worked assumptions, domestic hot water electrification closes approximately 40 percent of the gap while the boilers remain in service.
The heat pump produces the emissions reduction. Storage keeps the plant smaller than a morning-peak design and determines the electrical service, demand-charge exposure and basement layout. Compute the position with the City's projected 2030 factor, file the compliance schedule by May 1, 2027 if the plant will not be in place by then, and re-verify the ACP rate and grid factor before any figure goes to the board.